Monday, April 2, 2007

Construction Update - April 2, 2007


With the winter snows gone, construction at Black Bull is ramping up for another busy spring and summer. So far the construction is right on schedule. Here’s where we’re at:

Golf Course – Grading and irrigation of the Tom Weiskopf-designed golf course was nearly finished in 2006 and will be completed in early spring of 2007. In May, grassing of the tees, greens and fairways will begin in preparation for a soft opening in the late summer.

Swim and Tennis Center – RMR Group is progressing smoothly with the construction of the Swim and Tennis Center (which will serve as our temporary clubhouse). The framing is complete with mechanical, electrical, and plumbing trades well underway. The structure is scheduled to be complete by late summer and will have an opening to coincide with the golf course.

Infrastructure – Sime Construction has been working on the underground infrastructure since January 2007. Work has progressed smoothly and the completion date remains to be in mid-summer of 2007.

Club Home Models – RMR Group is also making great progress on the construction of two club home models that are slated for completion in late summer. Both homes have been framed and roofed with mechanical, electrical, and plumbing contractors working in them.

You can check out the website for more information on the Black Bull developers, the championship golf course, and all aspects of the project. More to follow soon!